New Construction schedule for Downtown Revitalization
Hiern (water and sewer) – start 12/1/09
W Second to Market (water and sewer) start 12/21/09
Pressure test, chlorination and bacterial testing all areas12/14/09
Video sewer mains – start 1/1/10
Drainage (CDBG) Hiern – start 11/30/09
Lighting (CDBG) Scenic – start installing conduit mid November
W Second and Woodman (water and sewer) – start 1/18/10
W Second and Woodman Drainage (CDBG) – start 2/22/10
St Paul to E Second (water and Sewer) – start 3/22/10
Landscaping (CDBG) – start 4/5/10
Railroad Alley (water and sewer) - start 4/19/10
Handy Street (water and sewer) – start 5/10/10
E Second (water and sewer) – start 5/10/10
Davis (water and sewer) – start 6/11/10
Fleitas (water and sewer) – start 7/5/10
E Second (water and sewer) – start 7/19/10
|